Multi-Sport

Holy Trinity Lutheran School Multi-Sport Court

South Tampa, FL

Project Case Study

Surface System
Acrytech Standard Acrylic
Project Duration
6 Weeks
Project Type
New Construction
Market
School

Project Summary

This project built a new multi-sport court from the ground up at Holy Trinity Lutheran School in South Tampa, Florida. The court sits on a reinforced concrete base with a thickened edge, finished in acrylic and striped for both volleyball and basketball. Six weeks from pour to finished surface.

Scope & Execution

This was a new build rather than a resurface. A reinforced concrete base was poured with a thickened edge to hold the perimeter against movement, which matters on a campus court that will take daily use rather than weekend play. The slab was then given the full cure it needed before any coating went down. An Acrytech acrylic system was applied and the court was striped for volleyball and basketball together. Six weeks from pour to finished surface, most of that time spent letting the concrete do what it needs to do.

Construction Considerations

Reinforced concrete base with a thickened perimeter edge
Full concrete cure allowed before any coating was applied
Volleyball and basketball striping on a single court
Layout planned for daily school use rather than occasional play

Unique Challenges

Building a new court inside an occupied school campus
Scheduling the pour and the cure around the school calendar
Fitting a regulation layout into the available campus footprint

Project Context

A Campus Court Built From the Base Up

A new reinforced court built on a school campus and striped for two sports, designed for daily use rather than occasional play.